Trovi qui elencate le risposte corrette della Verifica di Apprendimento con i relativi commenti.
Question 1
What is the expected duration of the Daily Scrum meeting?
Correct Answer: C.
Explanation: The Daily Scrum is a 15-minute time-boxed event intended to inspect progress toward the Sprint Goal. It should last no more than 15 minutes.
Question 2
Who is responsible for managing the Daily Scrum meetings?
Correct Answer: C.
Explanation: According to the Scrum Guide, the Developers are responsible for conducting and managing the Daily Scrum. They can choose the structure and techniques to achieve the meeting’s goals.
Question 3
How much time does each Developer have during the Daily Scrum?
Correct Answer: A.
Explanation: The Scrum Guide allows the Developers to determine how they will manage the meeting and their time during the Daily Scrum.
Question 4
The Developers must have the Scrum Board open and visible during the Daily Scrum.
Correct Answer: B.
Explanation: While a Scrum Board may help with visibility, it is not a requirement for the Daily Scrum as stated in the Scrum Guide.
Question 5
Which of the following statements about the Daily Scrum is FALSE?
Correct Answer: A.
Explanation: The time-box of the meeting is 15-minutes. This means that the meeting can also take less than 15-minutes. There is no need to use the entire time if the purpose of the meeting has been reached.
Question 6
Which is one likely consequence if the Scrum Team does not hold a regular Daily Scrum meeting?
Correct Answer: B.
Explanation: Without the Daily Scrum, the team loses essential opportunities to inspect progress and adapt their plan toward the Sprint Goal, potentially delaying feedback and problem-solving.
During the Sprint Review meeting, the Scrum Team demonstrates complete and incomplete Product Backlog Items and discusses what to do next.
Correct Answer: B.
Explanation: According to the Scrum Guide, only "done" work should be demonstrated in the Sprint Review. Demonstrating incomplete work may create the impression that it is complete and ready for release.
The Scrum Team meets with the Stakeholders at the end of the Sprint. What should the Product Owner do if a Product Backlog Item is only partially done?
Correct Answer: C.
Explanation: Incomplete work is not considered releasable. Any unfinished item should be moved back to the Product Backlog for future refinement and potential inclusion in subsequent Sprints.
What is the maximum duration of the Sprint Review meeting for a three-week Sprint?
Correct Answer: D.
Explanation: The Scrum Guide states that a Sprint Review for a one-month Sprint should be time-boxed to four hours. Shorter Sprints generally require proportionally shorter time boxes, although specific durations are not strictly enforced.
The Stakeholders have been complaining to the Scrum Master that the Sprint Review meeting is too long. To address this, the Scrum Team has created a presentation with slides of the completed features. Is this a good approach?
Correct Answer: C.
Explanation: The Sprint Review is intended as a hands-on inspection of the product, allowing stakeholders to interact directly with the Increment to provide meaningful feedback.
The Product Owner reviews work only during the Sprint Review meeting.
Correct Answer: B.
Explanation: Work is reviewed collaboratively throughout the Sprint, not just at the Sprint Review. This continuous inspection and feedback ensure that the Increment aligns with the Sprint Goal before reaching the Sprint Review.
The Sprint Review is the last prescribed Scrum event in the Sprint.
A) True
B) False
Correct Answer: B.
Explanation: The Sprint Retrospective is the last Scrum event in the Sprint, occurring after the Sprint Review to allow the Scrum Team to inspect and adapt their practices before the next Sprint.
The Stakeholders can participate in the Sprint Retrospective but only when invited by the Product Owner.
Correct Answer: B.
Explanation: The Sprint Retrospective is an internal event for the Scrum Team. No external participants are invited, ensuring a safe space for reflection.
When should the Sprint Retrospective take place?
Correct Answer: B.
Explanation: The Sprint Retrospective is mandatory at the end of each Sprint, providing a structured opportunity for the team to discuss improvements.
What should be the maximum duration of the Sprint Retrospective for a 2-week Sprint?
Correct Answer: D.
Explanation: The Scrum Guide prescribes a maximum of 3 hours duration for the Sprint Retrospective when the Sprint is one month long. Nevertheless, the event should be shorter if the Sprint is shorter than four weeks. However, the Scrum Guide does not say the event time-box should be proportional to the Sprint length.
Complete the following sentence:
The purpose of the Sprint Retrospective is to inspect how the last Sprint went with regards to _____
Correct Answer: B.
Explanation: The Sprint Retrospective focuses on inspecting processes, tools, relationships, and the Definition of Done, as a means of continuous improvement.
To reduce complexity, it can help if the Sprint Retrospective is held at the same time and place.
Correct Answer: A.
Explanation: Holding events at a consistent time and place simplifies team coordination, aligning with Scrum’s aim to minimize complexity.
What is the role of the Scrum Master in the Sprint Retrospective meeting?
Correct Answer: C.
Explanation: The Scrum Master is a member of the Scrum Team. Scrum Master is responsible for “ensuring that all Scrum events take place and are positive, productive, and kept within the timebox.” - Scrum Guide v2020.
The Sprint Retrospective must start with a short and fun activity to make everybody more relaxed and positive.
Correct Answer: B
Explanation: While fun activities are encouraged, the Scrum Guide does not mandate specific Retrospective activities; the team may choose any format that suits their needs.
Complete the following sentence:
By the end of the Sprint Retrospective, the Scrum Team _____
Correct Answer: B.
Explanation: The Retrospective concludes with identified improvements for immediate application in the following Sprint.
Complete the following sentence:
Over time, the Scrum Team uses the Sprint Retrospective to plan changes to the Definition of Done as a way to _______
Correct Answer: A
Explanation: Adjustments to the Definition of Done during Retrospectives aim to incrementally raise the overall Product quality.